EIR relative dates
You now need to associate each EIR with a date, relative to the dates in the appointing party's (client's) EIR. Note that, although deliverables specified in your lead appointed party EIR
You will need to consider the time required to review and authorize the information model(s) thinking also about any internal assurance processes. An example of a relative date for installation information may therefore be 85 working days prior to the client's end of construction stage information delivery milestone.
Please complete the table below to confirm the relative date for each EIR.